시작하기: 첫 번째 생산 주문
빈 모듈에서 완료된 생산 주문까지 15분.
1. 공장 설정(한 번만)
Step 1 Admin → Manufacturing → Work Centers
Create one work center per line/cell. Set daily capacity minutes.
Step 2 Admin → Manufacturing → BOMs
Create a BOM for a product you make: output item + component lines.
Publish a version (effective from today).
Step 3 (Optional) Routings
Add operation steps with setup/run times per work center —
the scheduler uses them; unrouted items still schedule fine.
Step 4 (Optional) Industry preset
Pick a preset (food, pharma, electronics…) to auto-activate
the compliance features your industry expects.
2. 일상业务流程 실행
Demand arrives (order, forecast or manual signal)
↓
Planned order proposed (MRP) → firm it when you agree
↓
Production order created → release to the floor
↓
Issue materials from stock → WIP tracked automatically
↓
Record output (good/graded/by-products)
↓
Quality inspection (if the item's policy requires it)
↓
Complete the order → finished goods enter inventory,
actual costs post to Accounting
모든 단계에서 실시간 이벤트가 발생하여 모든 사용자에게 대시보드와 보드가 실시간으로 업데이트됩니다.
3. 소규모 매장 바로가기
계획을 완전히 건너뛰고 생산 주문 → 신규, BOM, 수량 및 마감일을 선택하세요. 그 외의 항목(계획, 스케줄링, 예측)은 필요할 때까지 꺼 둬도 됩니다.
마지막 수정: 11/22/2026