البدء: طلب الإنتاج الأول الخاص بك
البدء: طلب الإنتاج الأول الخاص بك
خمسة عشر دقيقة من وحدة فارغة إلى طلب إنتاج مكتمل.
1. إعداد المصنع (مرة واحدة)
Step 1 Admin → Manufacturing → Work Centers
Create one work center per line/cell. Set daily capacity minutes.
Step 2 Admin → Manufacturing → BOMs
Create a BOM for a product you make: output item + component lines.
Publish a version (effective from today).
Step 3 (Optional) Routings
Add operation steps with setup/run times per work center —
the scheduler uses them; unrouted items still schedule fine.
Step 4 (Optional) Industry preset
Pick a preset (food, pharma, electronics…) to auto-activate
the compliance features your industry expects.
2. تشغيل التدفق اليومي
Demand arrives (order, forecast or manual signal)
↓
Planned order proposed (MRP) → firm it when you agree
↓
Production order created → release to the floor
↓
Issue materials from stock → WIP tracked automatically
↓
Record output (good/graded/by-products)
↓
Quality inspection (if the item's policy requires it)
↓
Complete the order → finished goods enter inventory,
actual costs post to Accounting
كل خطوة تطلق أحداث حية - يتم تحديث لوحات المعلومات واللوحات في الوقت الحقيقي للجميع الذين يشاهدون.
3. اختصار المحلات الصغيرة
تجاوز التخطيط تمامًا: طلبات الإنتاج → جديدة، اختر قائمة المواد، الكمية وتاريخ الاستحقاق. يمكن أن تظل كل الأشياء الأخرى (التخطيط، الجدولة، التنبؤ) مغلقة حتى تحتاج إليها.
Last updated: 8/27/2026